How to compare quotes from Indian suppliers
Unit price hides MOQ, tooling, freight and payment terms. A way to line up quotes so the cheapest offer is genuinely the cheapest.
13 September 2026 · Updated 28 October 2026 · 3 min read
Five quotes, five different questions
One quote includes tooling, one assumes a higher minimum order, one is ex-works, and one has added freight to a port you never named. The cheapest number is usually the least complete.
Comparison starts before the replies arrive: ask every supplier the same questions, in the same order, and put the answers in one layout.
Turn each offer into columns
Put every quote into this shape so gaps become visible:
- Unit price at your stated quantity.
- MOQ, and the price at your actual trial quantity.
- Tooling, setup or pattern cost, one time.
- Lead time after drawing approval and after purchase order.
- Payment terms and currency.
- Incoterm and named port.
- Packing, marking and pallet specification.
- How long the quote stays valid.
Add the costs that sit outside the unit price
Two suppliers can look twenty percent apart until the surrounding costs are counted:
- Freight and insurance, when the quote is ex-works or FOB.
- Import duty and taxes at your end.
- Third-party inspection, if you are paying for one.
- Bank charges on the transfer, easy to forget on small orders.
- Sorting or rework, if the first batch arrives with a defect rate nobody agreed.
Read lead time properly
Lead time from purchase order is not the same as lead time from drawing approval, and neither is the same as the date the goods leave the factory. Ask for the date the cargo is ready for pickup, then add transit.
A factory quoting 30 days and delivering in 45 is worse than one quoting 45 and delivering in 45, if your line needs the part in week six. Ask for the last three delivery dates on a similar order.
Compare the factory, not only the price
Two quotes can be identical and carry very different risk. One factory has made the part for years and can show a process sheet. The other is quoting from a drawing for the first time.
Look at verification, the machines named in the quote, and whether the contact answers technical questions directly or forwards every message to someone else. Price is the last column to read, not the first.
When the gap is very wide
A quote at half the others is usually one of four things: a different material, a smaller quantity break, a missing process step, or a mistake. Ask the supplier to walk through the cost. An honest factory will explain it. A rushed one will go quiet.
A quote well above the others often means low volume on that line, special tooling, or a broker sitting in the middle. Both ends deserve a second message before you decide.
A simple way to decide
Score each offer on price, lead time, completeness and evidence. Remove anything that fails a hard requirement such as certification or packing. Then compare what is left on total landed cost, not unit price.
If two offers finish close, take the factory that answered your questions best. You will be dealing with them for the life of the order, and a good technical reply is the cheapest insurance available.